Question

1 Approved Answer

The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead) based on 100% of

The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead) based on 100% of normal capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows:

Actual: Variable factory overhead

$360,000

Fixed factory overhead

104,000

Standard hours allowed for units produced: 60,000 hours

What is the amount of the fixed factory overhead volume variance?
a. $26,000 unfavorable
b. $14,000 unfavorable
c. $12,000 favorable
d. $12,000 unfavorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamental Accounting Principles Volume I

Authors: Kermit Larson, Tilly Jensen, Heidi Dieckmann

16th Canadian edition

978-1260305821

More Books

Students also viewed these Accounting questions

Question

What do you mean by dual mode operation?

Answered: 1 week ago

Question

Explain the difference between `==` and `===` in JavaScript.

Answered: 1 week ago