Question
The standard labor cost in the production of a pair ofRichettiBrand athletic shoes is0.40hours at $14.00per hour. During the month of June,24,630pairs were produced. Actual
The standard labor cost in the production of a pair ofRichettiBrand athletic shoes is0.40hours at $14.00per hour. During the month of June,24,630pairs were produced. Actual labor costs were $96,240for8,020hours. Compute the labor rate and labor efficiency variances for the month of June.(Round actual wage rate to 2 decimal places, e.g. 15.25 and final answers to 0 decimal places, e.g. 125. Enter all variances as a positive number.)
Labor Rate - Amount in $, Favorable, Unfavorable or Neither
Labor Efficiency Variance - Amount in $, Favorable, Unfavorable or Neither
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started