Question

1 Approved Answer

The standard Lost of Product B manufactured by Crane Company includes 2.8 units of direct materials at $6.70 per unit. During June, 27,000 units of

The standard Lost of Product B manufactured by Crane Company includes 2.8 units of direct materials at $6.70 per unit. During June, 27,000 units of direct materials are purchased at a cost of $6.50 per unit, and 27,000 units of direct materials are used to produce 9,600 units of Product B. (a) Compute the total materials variance and the price and quantity variances. Total materials variance

Materials price variance

Materials quantity variance

(b) Compute the total materials variance and the price and quantity variances, assuming the purchase price is $6.75 and the quantity purchased and used is 27,000 units.

Total materials variance

Materials price variance

Materials quantity variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Changing Academics Quality Audit And Its Perceived Impact

Authors: Ming Cheng

1st Edition

3639134273, 978-3639134278

More Books

Students also viewed these Accounting questions