The status data for a project after 2 5 weeks from project start is: Earned Value = 5 5 , Planned Value = 5 0

The status data for a project after 25 weeks from project start is: Earned Value =55, Planned Value =50, Actual Costs =60. The time variance at the status date is:

Step by Step Solution

There are 3 Steps involved in it