The steering committee originally mandated that cost was the most important factor to the project, keeping the project team size lean. As the project drags on, the steering committee shifts and tells the project manager that schedule is the most important factor to the project. This is an example of which type of influence on a project?
A. Change request
B. Constraint reprioritization
C. Scope creep
D. Interactions between constraints