The superintendent of a project wants to start the site work after completion of exterior paint not because there is a mandatory dependency between exterior

The superintendent of a project wants to start the site work after completion of exterior paint not because there is a mandatory dependency between exterior paint and site work, but because he prefers to have all of the scaffolding out of the way before getting started with site work. This type of relationship is referred to?
Group of answer choices
Soft Logic (Preferential)
Hard Logic (Mandatory)
Critical Logic
Resource Dependence Logic

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Project Management

Authors: Jack Gido, Jim Clements

4th Edition

9780324656152, 324656130, 978-0324656138

More Books

Students also viewed these General Management questions