Answered step by step
Verified Expert Solution
Question
1 Approved Answer
The table below lists the activities required to complete an equipment installation project. Also included are expected (normal) activity times and variances, precedence requirements, normal
The table below lists the activities required to complete an equipment installation project. Also included are expected (normal) activity times and variances, precedence requirements, normal costs at expected times, and the cost to expedite by 1 week. Any activity can only be expedited by 1 week maximum. Activity times in weeks) and variances are computed using most likely, optimistic, and pessimistic times. Activity's represents the start of the project, but it has no time or cost value. (a) Draw the network diagram, labeling all activities and times. What is the expected duration of the project? (b) What is the probability the project can be finished within 30 weeks? How much would it cost and which activities would you expedite to reduce the expected duration of the project by (c) 1 week? Activity Immediate predecessor Normal time Expedited time 1 0 0 1 1 4 Moment 2 e o co Expedited cost (5) 0 7,900 3,000 10,200 13,000 7,800 6,500 11,000 6 e tu UA N A Normal cost ($) 0 6,000 4,000 8,000 10,000 6,000 5,000 9,000 1000 6 7 2 = N 6 7,8 The table below lists the activities required to complete an equipment installation project. Also included are expected (normal) activity times and variances, precedence requirements, normal costs at expected times, and the cost to expedite by 1 week. Any activity can only be expedited by 1 week maximum. Activity times in weeks) and variances are computed using most likely, optimistic, and pessimistic times. Activity's represents the start of the project, but it has no time or cost value. (a) Draw the network diagram, labeling all activities and times. What is the expected duration of the project? (b) What is the probability the project can be finished within 30 weeks? How much would it cost and which activities would you expedite to reduce the expected duration of the project by (c) 1 week? Activity Immediate predecessor Normal time Expedited time 1 0 0 1 1 4 Moment 2 e o co Expedited cost (5) 0 7,900 3,000 10,200 13,000 7,800 6,500 11,000 6 e tu UA N A Normal cost ($) 0 6,000 4,000 8,000 10,000 6,000 5,000 9,000 1000 6 7 2 = N 6 7,8
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started