The table below provides cost and time estimates of seven activities of a project. Time estimates. Directcosts ActivityNormalCrash.Normalcrash (1,2) 2. 1. 10. 15 (1,3) 8.

The table below provides cost and time estimates of seven activities of a project.

Time estimates. Directcosts ActivityNormalCrash.Normalcrash

(1,2) 2. 1. 10. 15

(1,3) 8. 5. 15. 21

(2,4). 4. 3. 20. 24

(3,4) 1. 1. 7. 7

(3,5). 2. 1. 8. 15

(4,6). 5. 3. 10. 16

(5,6). 6. 2. 12. 36

(I) Draw the project network corresponding to normal time.

(ii) Determine the critical path and the normal duration and normal cost of the project.

(iii) Crash the activities so that the completion reduces to 9 weeks with minimum additional cost.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Forensic Accounting

Authors: Michael A Crain, William S Hopwood

2nd Edition

1948306441, 978-1948306447

Students also viewed these Accounting questions