The table below provides cost and time estimates of the seven activities of a project. Activity i-j Time Estimates (Weeks) Time Estimates (Weeks) Direct Cost

The table below provides cost and time estimates of the seven activities of a project.

Activity

i-j

Time Estimates

(Weeks)

Time Estimates

(Weeks)

Direct Cost Estimate

(KSHs. in 000)

Direct Cost Estimate

Crash Cost (KSHs. in 000)

1-2 2 1 10 15
1-3 8 5 15 21
2-4 4 3 20 24
3-4 1 1 7 7
3-5 2 1 8 15
4-6 5 3 10 16
5-6 6 2 12 36

i. Draw the project network corresponding to normal time.

ii. Determine the critical path and the normal duration and the normal costs of the project.

iii. Crash the activities so that the project completion time reduces to 9 weeks, with minimum additional cost.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these General Management questions

Question

=+does this differ from ethical conduct?

Answered: 1 week ago

Question

A loop with in another loop is called a ?

Answered: 1 week ago

Question

Java interpreter is also known as ?

Answered: 1 week ago

Question

Which purpose a construction is used?

Answered: 1 week ago

Question

The trim method of the string class removes..........?

Answered: 1 week ago

Question

Which type of data is not accessed in a derived class?

Answered: 1 week ago