The table below provides the parameters for a new current state value stream map for the family of retainers at the Jensen Bearings Inc. firm described in the chapter. This table depicts the value stream after Kline Steel agrees to accept daily orders for steel sheets and also agrees to deliver on a daily basis. Calculate each component of the new value stream's reduced lead time. Jensen Bearings operates 5 days per week. \begin{tabular}{|c|c|c|} \hline Attributes & \begin{tabular}{l} Batch size: 1,00 \\ Number of shifts \\ Availability: 8 ho \end{tabular} & \begin{tabular}{l} rs per shift with two 30 minute lunch breaks \\ rer 1 \end{tabular} \\ \hline Process Step 1 & Press & \begin{tabular}{l} Cycle time =6 seconds \\ Setup time =2 hours \\ Uptime =90% \\ Operators =1 \\ Every Part Every =1 week \\ WIP =1 day of sheets (before Press) \end{tabular} \\ \hline Process Step 2 & Pierce \& Form & \begin{tabular}{l} Cycle time =23 seconds \\ Setup time =30 minutes \\ Uptime =100% \\ Operators =1 \\ WIP =900 "L", 1,150 "S" (before Pierce \& Form) \end{tabular} \\ \hline Process Step 3 & Finish Grind & \begin{tabular}{l} Cycle time =36 seconds \\ Setup time =45 minutes \\ Uptime =100% \\ Operators =1 \\ WIP =300 " L",1,550 " S " (before Finish Grind) \end{tabular} \\ \hline Process Step 4 & Shipping & WIP =600 "L", 1,300 "S" (after Finish Grind) \\ \hline \begin{tabular}{l} Supplier \\ Information \end{tabular} & One shipment a & day in trays of 60 pieces \\ \hline Information Flow & All communicat & ns from customer are electronic: \\ \hline \end{tabular} \begin{tabular}{|c|c|c|} \hline Process Step 3 & Finish Grind & \begin{tabular}{l} Cycle time =36 seconds \\ Setup time =45 minutes \\ Uptime =100% \\ Operators =1 \\ WIP =300 "L", 1,550 "S" (before Finish Grind) \end{tabular} \\ \hline Process Step 4 & Shipping & WIP =600 "L", 1,300 "S" (after Finish Grind) \\ \hline \begin{tabular}{l} Supplier \\ Information \end{tabular} & \multicolumn{2}{|c|}{ One shipment a day in trays of 60 pieces } \\ \hline Information Flow & \multicolumn{2}{|c|}{\begin{tabular}{l} All communications from customer are electronic: \\ 180/90/60/30/day Forecasts \\ Daily Order \\ All communications to supplier are electronic \\ 4-week Forecast \\ Weekly Fax \\ There is a weekly schedule mahually delivered to Press, Pierce \& Form, and \\ Finish Grind and a Daily Ship Schedule manually delivered to Shipping \\ All material is pushed \end{tabular}} \\ \hline \end{tabular}