Question: The table below shows the activity sequencing of a software development project: a. Draw an activity-on-node (AON) network diagram for this project. (8) b.

The table below shows the activity sequencing of a software development project: a. Draw an activity-on-node

The table below shows the activity sequencing of a software development project: a. Draw an activity-on-node (AON) network diagram for this project. (8) b. How long is the "critical path"? (4) c. Suppose the project needs to be completed earlier than planned, what activity should be shortened and why? (2) Activity A B C D E F G H Description Concept design Business analysis System analysis System modelling Budgeting Developing Marketing Documenting Predecessor (None) A A A B B, C, D B E, F Duration (weeks) 2 6 4 2 4 3 2 Cost (S/day) 160 100 140 140 120 180 100 130

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a The activity on node diagram is attached b The critical path is 15 weeks l... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Programming Questions!