The table below shows the schedule for a new project for Nestl. Conduct a critical path analysis
Fantastic news! We've Found the answer you've been seeking!
Question:
The table below shows the schedule for a new project for Nestlé. Conduct a critical path analysis to highlight the critical path.
Activity | Activity Name | Dependent (Predecessor) | Duration (Weeks) |
A | Project Outline | - | 4 |
B | Assign Tasks | A | 2 |
C | Task Implementation | B | 3 |
D | Budget Designation | - | 6 |
E | Budget Allocation | D | 2 |
F | Budget Implementation | E | 2 |
G | Marketing Campaign | C, F | 4 |
H | R&D | - | 5 |
I | Product Development | H | 4 |
J | Product Launch | G, I | 2 |
Related Book For
Project management the managerial process
ISBN: 978-0073403342
5th edition
Authors: Eric W Larson, Clifford F. Gray
Posted Date: