Question

1 Approved Answer

The table shown below, which lists the normal and crash durations, and costs for a project, comprising of seven activities, and the network diagram

  

The table shown below, which lists the normal and crash durations, and costs for a project, comprising of seven activities, and the network diagram for said project. All durations are in days, and all costs are in dollars. The network diagram for the project is also shown below. 1 Activity Immediate Normal Normal Predecessor Duration Cost 6 100 10 3 4 4 7 2 ABCDEFG B J A B, C D D E 200 50 150 250 200 50 4 125 Crash Crash Duration Cost 4 500 10 200 2 300 4 150 450 200 100 71 F 3 7 1 Required: Determine a) The critical path; b) The normal duration and the normal cost of the project; and c) By how many days can this project be crashed, and at what cost,

Step by Step Solution

3.41 Rating (151 Votes )

There are 3 Steps involved in it

Step: 1

Activity ES EF LS LF SLACK A 0 6 1 7 1 B 0 10 0 10 0 C 6 9 7 10 1 D 10 14 10 14 0 E 14 18 15 19 1 F ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

10th Edition

978-047027870, 978-0-470-5038, 470278706, 978-0470278703

More Books

Students also viewed these Banking questions

Question

=+What are the actions in this decision process?

Answered: 1 week ago