Question

1 Approved Answer

The Taravez Company uses standard costing in its manufacturing plant for auto parts. The standard cost of a particular auto part, based on a denominator

The Taravez Company uses standard costing in its manufacturing plant for auto parts. The standard cost of a particular auto part, based on a denominator level of 3,900 output units per year, included 5 machine-hours of variable manufacturing overhead at $7 per hour and 5 machine-hours of fixed manufacturing overhead at $16 per hour. Actual output produced was 4,300 units. Variable manufacturing overhead incurred was $260,000. Fixed manufacturing overhead incurred was $265,000. Actual machine-hours were 30,000.

Requirements

1.

Prepare an analysis of all variable manufacturing overhead and fixed manufacturing overhead variances, using the 4-variance analysis.

2.

Prepare journal entries using the 4-variance analysis.

3.

Describe how individual fixed manufacturing overhead items are controlled from day to day.

4.

Discuss possible causes of the fixed manufacturing overhead variances.

Requirement 1. Prepare an analysis of all variable manufacturing overhead and fixed manufacturing overhead variances, using the 4-variance analysis. Begin by calculating the following amounts for the variable overhead.

Actual Input

Actual Costs

x

Flexible

Allocated

Incurred

Budgeted Rate

Budget

Overhead

Variable OH

Now complete the table below for the fixed manufacturing overhead.

Same Budgeted

Lump Sum

Actual Costs

Regardless of

Flexible

Allocated

Incurred

Output Level

Budget

Overhead

Fixed OH

Now complete the 4-variance analysis using the amounts you calculated above. (If no variance exists, leave the dollar value blank. Label the variance as favorable (F), unfavorable (U) or never a variance (N).)

4-Variance

Spending

Efficiency

Production-Volume

Analysis

Variance

Variance

Variance

Variable OH

Fixed OH

Requirement 2. Prepare journal entries using the 4-variance analysis. Record the actual variable

manufacturing overhead incurred. (Record debits first, then credits. Exclude explanations from any journal entries.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions