The team is working on determining the order and linkage between tasks on the project. There is a field survey going on that reaches out
The team is working on determining the order and linkage between tasks on the project. There is a field survey going on that reaches out to customers. One team member started the report for this work while the survey was still being done but said it will be about one week after the survey is complete for the report to be complete. This is an example of
A Starttofinish relationship
B Finishtofinish relationship
Starttostart relationship
D
Finishtostart relationship