Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The technique for calculating a bid price can be extended to many other types of The technique for calculating a bid price can be extended

The technique for calculating a bid price can be extended to many other types of The technique for calculating a bid price can be extended to many other types of
problems. Answer the following questions using the same technique as setting a bid
price; that is, set the project NPV to zero and solve for the variable in question. Martin
Enterprises needs someone to supply it with 154,000 cartons of machine screws per
year to support its manufacturing needs over the next five years, and you've decided to
bid on the contract. It will cost $1,940,000 to install the equipment necessary to start
production; you'll depreciate this cost straight-line to zero over the project's life. You
estimate that, in five years, this equipment can be salvaged for $164,000. Your fixed
production costs will be $279,000 per year, and your variable production costs should
be $10.80 per carton. You also need an initial investment in net working capital of
$144,000. The tax rate is 24 percent and you require a return of 13 percent on your
investment. Assume that the price per carton is $17.40.
a. Calculate the project NPV.(Do not round intermediate calculations and round your
answer to 2 decimal places, e.g.,32.16.)
b. What is the minimum number of cartons per year that can be supplied and still break
even? (Do not round intermediate calculations and round your answer to the
nearest whole number, e.g.,32.)
c. What are the highest fixed costs that could be incurred and still break even? (Do not
round intermediate calculations and round your answer to 2 decimal places, e.g.,
32.16.)problems. Answer the following questions using the same technique as setting a bid price; that is, set the project NPV to zero and solve for the variable in question. Martin Enterprises needs someone to supply it with 154,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and youve decided to bid on the contract. It will cost $1,940,000 to install the equipment necessary to start production; youll depreciate this cost straight-line to zero over the projects life. You estimate that, in five years, this equipment can be salvaged for $164,000. Your fixed production costs will be $279,000 per year, and your variable production costs should be $10.80 per carton. You also need an initial investment in net working capital of $144,000. The tax rate is 24 percent and you require a return of 13 percent on your investment. Assume that the price per carton is $17.40.
a.
Calculate the project NPV.(Do not round intermediate calculations and round your answer to 2 decimal places, e.g.,32.16.)
b.
What is the minimum number of cartons per year that can be supplied and still break even? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g.,32.)
c.
What are the highest fixed costs that could be incurred and still break even? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g.,32.16.)
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Handbook Of Financing Growth

Authors: Kenneth H. Marks, Larry E. Robbins, Gonzalo Fernandez, John P. Funkhouser, D. L. Williams

2nd Edition

0470390158, 978-0470390153

More Books

Students also viewed these Finance questions