The TEMKO Company encountered the problem of defects in some of its purchased tractor short-block castings. The short-block castings are used to build the R-208

The TEMKO Company encountered the problem of defects in some of its purchased tractor short-block castings. The short-block castings are used to build the R-208 tractor engines. TEMKO installs the heads, manifold, carburetor, and other engine parts, which consist of approximately 13 percent of the short-block casting purchase price. When the defects are discovered, the short blocks have to be disassembled and repaired. It takes approximately eight hours per repair. Even with this process, almost 4 percent of the incoming short blocks end up as scrap. In other words, approximately 10 out of every 100 units are repaired and 40 percent of the repaired short blocks are scrapped. Each short-block casting costs between $1,550 and $1,700 depending on the supplier. There is also a cost of downtime associated with interruptions on the shop floor.

The internal labor cost of assembling each incoming short-block casting and repair as necessary is approximately $878 per short block. The estimated overhead, which is 150 percent of direct labor, consists of 33 percent variable and 67 percent fixed costs; the shop floor disruption cost is estimated to be $500 per disruption.

Recently, James Sun, the purchasing manager, released a request for quote (RFQ) for the short blocks to three prequalified suppliers of assembled tractor engines. However, only one supplier, ACE Manufacturing, Inc., showed an interest. ACE was a small startup company that was looking for work. In order to produce assembled R-208 engines, an investment in precision machinery of more than $1,500,000 would need to be made. ACE was willing to both invest in the necessary machine and guarantee at least 100 engines per monthprovided TEMKO would contract with it as asole sourcefor the engines for the next three years. The price per engine would be $3,500 the first year, with an annual increase of 3 percent. TEMKO anticipated that they would need at least 1,000finishedengine assemblies per year for the next five years.

  1. Based on the information provided in the case study, calculate the current total cost/unit of the purchased item (i.e. short-block casting) in TEMKO each year. Explain your calculations in detail.
  2. What solutions do you recommend to the procurement team to resolve this problem in short- term and long-term.
  3. What would be the benefits and risks of switching to the new supplier, ACE, considering all the requirements, conditions and costs provided by them

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Financial Management

Authors: Eugene F. Brigham, Joel F. Houston

13th edition

978-1285027371, 128502737X, 978-1133541141

More Books

Students also viewed these Finance questions

Question

=+d) How many treatments are involved?

Answered: 1 week ago

Question

Create a Fishbone diagram with the problem being coal "mine safety

Answered: 1 week ago

Question

what is trade debtor?

Answered: 1 week ago