Question

1 Approved Answer

The Templeton Manufacturing and Distribution Company of Tacoma, Washington, is contemplating the purchase of a new conveyor belt system for one of its regional distribution

The Templeton Manufacturing and Distribution Company of Tacoma, Washington, is contemplating the purchase of a new conveyor belt system for one of its regional distribution facilities. Both alternatives will accomplish the same task but the Eclipse Model is substantially more expensive than the Sabre Model and will not have to be replaced for 10 years, whereas the cheaper model will need to be replaced in just 5 years. The costs of purchasing the two systems and the costs of operating them annually over their expected lives is provided below:

Year

Eclipse

Sabre

0

$(1,500,000)

$(850,000)

1

(26,000)

(48,000)

2

(28,000)

(48,000)

3

(28,000)

(58,000)

4

(28,000)

(58,000)

5

(38,000)

(75,000)

6

(38,000)

7

(38,000)

8

(38,000)

9

(38,000)

10

(38,000)

a.Templeton typically evaluates investments in plant improvements using a required rate of return of 11 percent.

What are the NPVs for the two systems?

b.Calculate the equivalent annual costs for the two systems.

c.Based on your analysis of the two systems using both their NPV and EAC, which system do you recommend the company pick? Why?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Management Theory And Practice

Authors: Eugene F Brigham, Michael C Ehrhardt

11th Edition

0324259689, 9780324259681

More Books

Students also viewed these Finance questions