The third step in activity - based costing is to identify the activities and assign budgeted costs to activity cost pools. allocate costs to cost
The third step in activitybased costing is to
identify the activities and assign budgeted costs to activity cost pools.
allocate costs to cost objects.
compute an overhead activity rate for each activity cost pool.