The Tigasin Concrete Company has three plants in different locations and is presently working on three construction projects, each located at a different site. Weekly

The Tigasin Concrete Company has three plants in different locations and is presently working on three construction projects, each located at a different site. Weekly capacities and project requirements are as follows.

Plant Capacity

A 400

B 500

C 600

Project Requirement

1 700

2 450

3 350

The shipping costs from the plants to the projects are given in the following table:

Project 1 Project 2 Project 3

Plant A 12 6 13

Plant B 11 7 10

Plant C 10 9 8

Find a routing plan that minimizes total transportation cost.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quality Of The Environment An Economic Approach To Some Problems In Using Land, Water, And Air

Authors: Orris C Herfindahl, Allen V Kneese

1st Edition

1317386663, 9781317386667

More Books

Students also viewed these Economics questions

Question

Population

Answered: 1 week ago

Question

The feeling of boredom.

Answered: 1 week ago