The time required to complete a project is known to be normally distributed with a mean of 44 weeks and a standard deviation of 8

image text in transcribed
The time required to complete a project is known to be normally distributed with a mean of 44 weeks and a standard deviation of 8 weeks. What is the probability that the project will take longer than 40 weeks to finish? 0.84 0.31 0.16 h 0.69 None of the above

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Management Of Business Finance

Authors: John Freear

1st Edition

0273014315, 978-0273014317

More Books

Students also viewed these Finance questions