The time required to complete a project is known to be normally distributed with a mean of 44 weeks and a standard deviation of 8

image text in transcribed
The time required to complete a project is known to be normally distributed with a mean of 44 weeks and a standard deviation of 8 weeks. There is a 90 percent chance that the project will be finished in fewer than approximately how many weeks? 54 45 60 W 38 44