Question

1 Approved Answer

The time to complete 1 construction project for company A is exponentially distributed with a mean of 1 year. Therefore: (a) What is the probability

The time to complete 1 construction project for company A is exponentially distributed with a mean of 1 year. Therefore:

(a) What is the probability that a project will be finished in one and half years?

(b) What is the probability a project will take more than one year but less than two years?

(c) If company A works on projects nonstop, what is the probability that four projects will be finished in three years?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Discrete and Combinatorial Mathematics An Applied Introduction

Authors: Ralph P. Grimaldi

5th edition

201726343, 978-0201726343

More Books

Students also viewed these Mathematics questions

Question

What are the main tasks involved in order processing?

Answered: 1 week ago