The time-phased net requirements for the base assembly in a table lamp over the next six weeks are: Week 1 2 3 4 5 6
The time-phased net requirements for the base assembly in a table lamp over the next six weeks are:
Week | 1 | 2 | 3 | 4 | 5 | 6 |
Requirements | 335 | 240 | 180 | 320 | 320 | 200 |
The setup cost for the construction of the base assembly is $200, and the holding cost is $0.30 per assembly per week.
a) What lot sizing do you obtain from the EOQ formula?
b) Determine the lot sizes using the SilverMeal heuristic.
c) Determine the lot sizes using the Least Unit Cost heuristic.
d) Determine the lot sizes using Part Period Balancing.
e) Determine the lot size using the WagnerWhitin algorithm.
f) Compare the holding and setup costs obtained over the six periods using the policies found in parts (a) through (e) with the cost of a lot-for-lot policy.
show formulas please.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started