Question

...
1 Approved Answer

The university IT team is working on the implementation of a new software system for enrollment. Using the following table, complete the requested tasks: Time

The university IT team is working on the implementation of a new software system for enrollment. Using the following table, complete the requested tasks:
Time in days Costs
Activity Immediate Predecessor Normal Crash Normal Crash
A - 6 5 $900 $1,000
B A 8 6 $300 $400
C A 4 3 $500 $600
D B 5 3 $900 $1,200
E C, D 8 5 $1,000 $1,600
a. Draw the network diagram noting normal and crash times.
b. What is the critical path?
c. What is the minimum cost of crashing the project by 4 days? Would you recommend the team crash the project? Explain your calculations and position.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Modern Database Management

Authors: Jeff Hoffer, Ramesh Venkataraman, Heikki Topi

12th edition

978-0133544619

Students also viewed these General Management questions