The U.S. Army Corps of Engineers has taken the lead in the area of ADR, and in particular: A)Arbitration B)Minitrials C)Conciliation 2.If the contracting officer
- The U.S. Army Corps of Engineers has taken the lead in the area of ADR, and in particular:
A)Arbitration B)Minitrials C)Conciliation
2.If the contracting officer does not issue a decision on a claim within a specified time, the contractor may:
A)Ask the Board of Contract Appeals to direct the contracting officer to issue a decision within a specified period of time B)Either of the above
3.When a final decision is appealed to the Armed Services Board of Contract Appeals, the contracting officer, in cooperation with the attorney/advisor, must submit within __________ to the ASBCA and the contractor an appeal file.
A)7 days B)14 days C)30 days
4.Under a contract for commercial items, the contracting officer may not:
B)Reject work after acceptanceC)Send a cure noticeD)Impose liquidated damagesE)None of the above
5.Under contracts for non-commercial items or services, the contracting officer may not:
A)Accept deliveries more than 90 days lateB)Withhold more than 10% of the monies due the contractor D)Assess any remedies for loss or damage to government property under a cost-plus-incentive-fee contractE)None of the above
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started