The Valley Corporation is developing a new product that could potentially capture a large market share. Management is anxious to introduce this new product to
The Valley Corporation is developing a new product that could potentially capture a large market share. Management is anxious to introduce this new product to market and, as a result, has asked you to prepare a complete analysis to meet a goal of 30 weeks or fewer.
Below is Valley Corporation's project network for this new product:
The activity time estimates are as follows (in weeks):
Activity | Optimistic | Most Likely | Pessimistic |
---|---|---|---|
A | 3.0 | 4.0 | 5.0 |
B | 3.0 | 3.5 | 7.0 |
C | 4.0 | 5.0 | 6.0 |
D | 2.0 | 3.0 | 4.0 |
E | 6.0 | 10.0 | 14.0 |
F | 7.5 | 8.5 | 12.5 |
G | 4.5 | 6.0 | 7.5 |
H | 5.0 | 6.0 | 13.0 |
I | 2.0 | 2.5 | 6.0 |
J | 4.0 | 5.0 | 6.0 |
1. Develop an activity schedule for this new product, and identify the critical path activities. What are the ES, EF, LS, LF and slack of the activies?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started