Question
The Watts Company uses a predetermined overhead rate to apply manufacturing overhead to jobs. The predetermined overhead rate is based on labour cost. The following
The Watts Company uses a predetermined overhead rate to apply manufacturing overhead to jobs. The predetermined overhead rate is based on labour cost. The following estimates were made at the beginning of the year and the actuals were recorded at the end of the year:
Estimates Actuals
Direct labour cost $30,000 $35,000
Manufacturing overhead $60,000 $77,000
Direct labour hours 6,000 7,000
Machine hours 2,000 4,000
Job 406 was completed on December 31. It contained $400 in DM, and $970 in DL. It required 49 DLH and 12 MH. What was the cost of Job 406?
Multiple Choice
- $1,940
- $3,310
- $3,504
- $2,134
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started