The Winnipeg Police Department has five detective squads available for assignment to five open crime cases. The chief of detectives, Paul Kuzdrall, wishes to assign

The Winnipeg Police Department has five detective squads available for assignment to five open crime cases. The chief of detectives, Paul Kuzdrall, wishes to assign the squads so that the total time to conclude the cases is minimized. The average number of days, based on past performance, for each squad to complete each case is as follows:

Case

Squad A B C D E
1 14 7 3 7 27
2 20 7 12 6 30
3 10 3 4 5 21
4 8 12 7 12 21
5 13 25 24 26 8

Each squad is composed of different types of specialists, and whereas on squad may be very effective in certain types of cases, it may be almost useless in others.

  1. Solve the problem by using the assignment method
  2. Assign the squads to the above cases, but with the constraint that squad 5 cannot work on cases E because of a conflict.

15.12

A Northern British Columbia lumberyard has four jobs on order, as sown in the following table. Today is day 205 n the yard's schedule.

Job Due Date Remaining time (days)
A 212 6
B 209 3
C 208 3
D 210 8

In what sequence would the jobs be ranked according to the following decision rules

  1. FCFS
  2. SPT
  3. LPT
  4. EDD
  5. Critical ratio

Which is best and why" which has the minimum lateness?

15.15

Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for (1) cutting and sewing and (2) delivery of each of the suits. Which schedule finishes sooner. First-come, first-served (123) or a schedule using Johnson's rule?

Times Taken for Different Activities (hours)

Suit Cut and Sew Deliver
1 4 2
2 7 7
3 6 5

15.16

The following jobs are waiting to be processed at Jeremy LaMontagne's machine centre. Today is day 250.

Job Date job received Production days needed Date job due
1 215 30 260
2 220 20 290
3 225 40 300
4 240 50 320
5 250 20 340

Using the critical-ratio scheduling rule, in what sequences would the jobs be processed?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing A Practical Approach

Authors: Robyn Moroney

1st Canadian Edition

978-1118472972, 1118472977, 978-1742165943

Students also viewed these Mathematics questions

Question

Why do we forget information?

Answered: 1 week ago