Question
The WLJ Boat ?Company, which is under contract to the U.S.? Navy, assembles troop deployment boats. LOADING... ?(Click the icon to view the additional? information.)
The WLJ Boat ?Company, which is under contract to the U.S.? Navy, assembles troop deployment boats. LOADING... ?(Click the icon to view the additional? information.) WLJ Boat reports the following cost information for the first PT109 assembled. LOADING... ?(Click the icon to view the cost? information.) Read the requirements LOADING... . Requirement 1. Prepare a prediction of the total costs for producing the six PT109s for the Navy. Begin by calculating the cumulative total time in? labor-hours. ?(Round the individual unit time for Xth unit to the nearest whole? number.) Number of Individual unit time for Cumulative total time: units Xth unit: Labor-hours Labor-hours 1 2 3 4 5 6 7
As part of its research? program, it completes the assembly of the first of a new model? (PT109) of deployment boats. The Navy is impressed with the PT109. It requests that
WLJ Boat
submit a proposal on the cost of producing another six PT109s.
WLJ Boat
reports the following cost information for the first PT109 assembled.
Direct material cost | $198,000 | |
Direct manufacturing labor time for first boat | 15,600 | ?labor-hours |
Direct manufacturing labor rate | ?$37 | per direct manufacturing? labor-hour |
Variable manufacturing overhead cost | ?$27 | per direct manufacturing? labor-hour |
Other manufacturing overhead | 20% | of direct manufacturing labor costs |
Tooling costsSuperscript aa | $278,000 | |
Learning curve for manufacturing labor time per boat | 90?% | incremental ?unit-timeSuperscript bb |
Superscript aa | Tooling can be reused at no extra cost because all of its cost has been assigned to the first deployment boat. |
Superscript bb | Using the formula for a 90?% learning? curve, StartFraction ln 0.90 Over ln 2 EndFraction equals StartFraction negative 0.105361 Over 0.693147 EndFraction equals negative 0.152004ln 0.90ln 2=?0.105361 0.693147=?0.152004 |
WLJ Boat uses a 90?% incremental? unit-time learning model as a basis for predicting direct manufacturing?labor-hours in its assembling operations.? (A 90?% learning curve means b? = ?0.152004?.)
1. Prepare a prediction of the total costs for producing the six PT109s for the Navy.
2. Compare the cost predictions from requirement 1? (incremental unit-time learning?model) with the cost predictions based on a cumulative? average-time learning model which has total costs of $5,874,625.
Why are the predictions? different? How should WLJ Boat decide which model it should? use?
Number of
Cumulative average time
Cumulative total time:
units
per unit: Labor-hours
Labor-hours
units
Xth unit: Labor-hours
Labor-hours
1
15,600
15,600
2
14,040
29,640
3
13,201
42,841
4
12,636
55,477
5
12,215
67,692
6
11,881
79,573
7
11,606
91,179
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started