Question
The Woods Enterprises prepared the following standard costs for the production of one stuffed bear: Direct materials 1.5 pounds of stuffing @ $2 per lb
The Woods Enterprises prepared the following standard costs for the production of one stuffed bear:
Direct materials 1.5 pounds of stuffing @ $2 per lb
Direct labor 2 hours of assembly @ $15 per hr
Actual production costs for the production of 1,000 stuffed bears required 1,750 pounds of stuffing at a cost of $1.95 per pound and 1,950 labor hours at $15.25 per hour.
A.) Calculate the direct material price variance.
B.) Calculate the direct material usage variance.
c) calculate the direct labor rate variance
d) calculate the direct labor efficiency variance
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started