The work breakdown structure for building a house (levels 1 and 2) is shown below: Level 1 Level 2a) To provide more detail to the
The work breakdown structure for building a house (levels 1 and 2) is shown below: Level 1 Level 2a) To provide more detail to the WBS, for the plumbing activity the appropriate next level activities could be: A. Underground Pipes B. Toilets and Sinks C. Irrigation System D. All of the above