Question

1 Approved Answer

The work component at the lowest level of the WBS for which cost and duration can be estimated and managed is called the ( 1

The work component at the lowest level of the WBS for which cost and duration can be estimated and managed is called the
(1pts)
activity
control
account
work package
work element
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Supply Chain Management A Logistics Perspective

Authors: John coyle, John Langley, Robert Novack, Brain Gibson

9th edition

9780538479189, 9781285400945, 538479191, 538479183, 1285400941, 978-0538479196

More Books

Students also viewed these General Management questions