TheproductionlineofproductXisdescribed below.504units ofproductXmustbeproduced daily with production time being 7 hours per day. Design a line that minimized the number ofworkstations based on the cycle time

TheproductionlineofproductXisdescribed below.504units ofproductXmustbeproduced daily with production time being 7 hours per day. Design a line that minimized the number ofworkstations based on the cycle time and the precedence of thetasks.

Task

Task Time (Seconds)

Immediate predecessor

A

45

-

B

11

A

C

9

B

D

50

-

E

26

D

F

11

E

G

12

C

H

10

C

I

9

F, G, H

J

10

I

  1. Draw a precedencediagram
  2. Calculate cycletime.
  3. Calculate the minimum number ofworkstations.
  4. Balance the assembly line using maximum number of followers, in case of a tie use highest positionalweight.
  5. Calculate Efficiency of theline.
  6. Calculate idle time inseconds.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions