There are four activities on the critical path. Coincidentally, their standard deviations are all equal to 4 . The standard deviation of the critical p
There are four activities on the critical path. Coincidentally, their standard deviations are all equal to 4 . The standard deviation of the critical p Multiple Choice 8. 2. 4. 64. 16