There are four critical paths in a network. A-B-C-D-E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of

There are four critical paths in a network. A-B-C-D-E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of 6 weeks. The crashing cost (per week), for the first week (crashing first time), for activity A is: $440, E is $455 and all other activities is : $110 (per week per activity). The crashing cost, second week and onwards(crashing second time), for activity A is $1100 per week, E is $1320 per week and for all other activities is $220 per activity per week. You have a maximum crashing budget of $2755. The maximum possible reduction in the project duration will be:

a.5 weeks

b.4 weeks

c.6 weeks

d.2 week

e.3 weeks

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Forecasting

Authors: John E. Hanke, Dean Wichern

9th edition

132301202, 978-0132301206

Students also viewed these General Management questions

Question

Have I comparison shopped for price and quality?

Answered: 1 week ago