Question

1 Approved Answer

There are four resources and four jobs to be done. Assume there must be one - to - one matching between jobs and resources. The

There are four resources and four jobs to be done. Assume there must be one-to-one matching between jobs and resources. The time required for each resource to do each job is as follows:
\table[[,Job (Hours)],[Resource,A,B,C,D],[1,5,8,7,7],[2,4,9,5,9],[3,6,9,8,7],[4,7,6,6,9]]
For the optimal schedule, what is the total number of hours required to complete these jobs?
Multiple Choice
20 hours
22 hours
19 hours
21 hours
23 hours
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions