There are six jobs in a factory. All these jobs have to go through two workstations for processing. Each job is processed on Workstation #

There are six jobs in a factory. All these jobs have to go through two workstations for processing. Each job is processed on Workstation #1 and then on Workstation #2. The processing time for each job on each workstation is given below.
\table[[Job,Time on Workstation #1(minutes),Time on Workstation #2(minutes)],[1,25,11],[2,50,25],[3,10,39],[4,13,20],[5,43,50],[6,13,9]]
Using Johnson's sequencing rule, it can be concluded that the makespan of the sequence is:
a. more than 115 but less than or equal to 140 minutes.
b. more than 140 but less than or equal to 160 minutes.
c. more than 160 but less than or equal to 180 minutes.
d. more than 180 but less than or equal to 205 minutes.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Mathematical Interest Theory

Authors: Leslie Jane, James Daniel, Federer Vaaler

3rd Edition

147046568X, 978-1470465681

Students also viewed these General Management questions