There are six jobs in a factory. All these jobs have to go through two workstations for processing. Each job is processed on Workstation #

There are six jobs in a factory. All these jobs have to go through two workstations for processing. Each job is processed on Workstation #1 and then on Workstation #2. The processing time for each job on each workstation is given below.
Job
Time on Workstation #1(minutes)
Time on Workstation #2(minutes)
1
26
42
2
22
10
3
8
29
4
26
16
5
43
45
6
40
29
Using Johnson's sequencing rule, it can be concluded that the makespan of the sequence is:
a. more than 130 but less than or equal to 155 minutes.
b. more than 155 but less than or equal to 175 minutes.
c. more than 175 but less than or equal to 195 minutes.
d. more than 195 but less than or equal to 220 minutes.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Bears Of The World Ecology Conservation And Management

Authors: Vincenzo Penteriani, Mario Melletti

1st Edition

1108483526, 978-1108483520

More Books

Students also viewed these General Management questions