There are six jobs in a factory. All these jobs have to go through two workstations for processing. Each job is processed on Workstation #
There are six jobs in a factory. All these jobs have to go through two workstations for processing. Each job is processed on Workstation # and then on Workstation # The processing time for each job on each workstation is given below.
Job
Time on Workstation #minutes
Time on Workstation #minutes
Using Johnson's sequencing rule, it can be concluded that the makespan of the sequence is:
a more than but less than or equal to minutes.
b more than but less than or equal to minutes.
c more than but less than or equal to minutes.
d more than but less than or equal to minutes.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started