There are three resource types available for a certain project. One unit of each resource type is available. The project manager wants to evaluate the

There are three resource types available for a certain project. One unit of each resource type is available. The project manager wants to evaluate the project cost on the basis of how resource teams are made up. She has the option of using a resource team, where the team can consist of only one resource type or a combination of resource types. If the team consists of more than one resource type, the resources will start and stop working at the same time. Fractions of a work day are permissive with prorated cost.

Resource 1 can complete the project alone in 50 days at a cost of $2500/day.

Resource 2 can complete the project alone in 35 days at a cost of $5750/day.

Resource 3 can complete the project alone in 75 days at a cost of $1500/day.

The resources produce identical quality of work.

(a) Determine the team composition that will yield the minimum project cost.

(b) What is the project duration corresponding to that minimum cost? Plot all the project costs versus the respective project durations.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Management for Public Health and Not for Profit Organizations

Authors: Steven A. Finkler, Thad Calabrese

4th edition

133060411, 132805669, 9780133060416, 978-0132805667

More Books

Students also viewed these General Management questions

Question

What is a flexible budget?

Answered: 1 week ago