There are two assignments (below). Your assignment is to do the following problems at the end of chapter 11. You will have to either draw

There are two assignments (below).

Your assignment is to do the following problems at the end of chapter 11. You will have to either draw a picture in Word or take a picture and attach it so I can see your work: Items without the scan or drawing will lose points.

Problem #1

Seth is the personnel director at a consulting company. He is considering a leadership program for managers at a client company. There are a number of activities that must be completed before the program can be conducted, and he has the time needed for each activity (below).

Develop a network for this problem.

Determine the total project completion time and the critical path(s).

Activity

Immediate Predecessors

Time (Days)

A

-

2

B

-

5

C

-

1

D

B

10

E

A, D

3

F

C

6

G

E, F

8

Problem #2

Develop a network for the problem (below).

Determine the total project completion time and the critical path(s).

Activity

Immediate Predecessors

Time (Days)

A

-

3

B

-

7

C

A

4

D

B

2

E

C, D

5

F

A

6

G

E, F

3

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Foundations In Personal Finance

Authors: Dave Ramsey

College Edition

1936948001, 978-1936948000

More Books

Students also viewed these Finance questions

Question

Fixed dollar match: 75 cents per each $1 employee contribution.

Answered: 1 week ago