There is a project with the following requirements: Task Duration (in days) Dependency A 5 B 3 C 7 A D 8 B E 5
- There is a project with the following requirements:
Task | Duration (in days) | Dependency |
A | 5 | |
B | 3 | |
C | 7 | A |
D | 8 | B |
E | 5 | C & D |
F | 9 | E |
G | 6 | E |
- Draw the diagram to denote the total project schedule (this can be done on paper and copy and paste the image in this word document or any other tool).
- Answer the following questions:
- What path is the critical path?
- How many other paths are there? Note them.
- What is the float/ slack in the schedule?
What is the early start, late start, early finish, and late finish of the project?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started