There is an 8 0 percent chance the following project can be completed in X weeks or less. A network diagram flowchart. The flows are

There is an 80 percent chance the following project can be completed in X weeks or less.
A network diagram flowchart. The flows are as follows. A, B, and D. A, C, and E.
ACTIVITY MOST OPTIMISTIC MOST LIKELY MOST PESSIMISTIC
A 2514
B 144
C 417
D 4611
E 4914
What is X?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management With CompTIA Project+

Authors: Joseph Phillips

4th Edition

9781259860300

More Books

Students also viewed these General Management questions

Question

2. Given ex2dx=, what is the value of e21x2dx [2]

Answered: 1 week ago

Question

=+What about SRI funds? Why, or why not?

Answered: 1 week ago