This assignment is NO less than 3 pages of content. APA formatting with citations and reference page. 12 pt font; double- space. Wedding cost estimation:
This assignment is NO less than 3 pages of content. APA formatting with citations and reference page. 12 pt font; double- space.
- Wedding cost estimation: Given the following information, calculate the estimated costs for a wedding with 250 guests and a bridal party of six, using the methods Show your work. Note that members of the bridal party are already counted as guests, you don't need to add them twice.
- Parametric estimate
- Bottom-up estimate
- Analogous cost estimate
- You will probably notice some differences in the estimated values. Are these differences significant? What might cause the differences? If you were estimating a significant project in the future, which method(s) would you use and why?
- Your mother points out you should probably have valet parking, which will cost $500. Which estimate(s) will change?
Wedding Cost Estimates | |
Item | Dollars |
Groom's brother's wedding, last year, 175 guests, similar venue and style | $20,300 |
Catering | $65 per person |
Photographer | $1,500 |
Rental of hall | $500 |
Clothing, bride | $2,000 |
Clothing, groom | $750 |
Flowers | $800 |
Other dcor items | $500 |
Cake | $500 |
Gifts for bridal party | $80 each |
Wedding planner | $2,000 |
Wedding planner's estimate of typical cost for this kind of wedding | $10,000 plus $75 per guest |
2. Earned-value analysis. A project budget calls for the following expenditures:
Task | Date | Budgeted Amount |
Build forms | April 1 | $10,000 |
April 1 | $50,000 | |
Pour foundation | May 1 | $100,000 |
May 1 | $30,000 | |
Frame walls | June 1 | $30,000 |
Remaining tasks | July 1 and beyond | $500,000 |
Define each term in your own words, calculate these values for the above project, and show your work:
- Budgeted cost baseline (make a graph illustrating this one)
- Budget at completion (BAC)
- Planned value (PV) as of May 1
- Earned value (EV) as of May 1 if the foundation work is only two-thirds Everything else is on schedule.
- SV as of May
- Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May
- Schedule performance index (SPI)
- Cost performance index (CPI)
- Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
- Estimate at completion (EAC)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started