Question

1 Approved Answer

This assignment is NO less than 3 pages of content. APA formatting with citations and reference page. 12 pt font; double- space. Wedding cost estimation:

This assignment is NO less than 3 pages of content. APA formatting with citations and reference page. 12 pt font; double- space.

  1. Wedding cost estimation: Given the following information, calculate the estimated costs for a wedding with 250 guests and a bridal party of six, using the methods Show your work. Note that members of the bridal party are already counted as guests, you don't need to add them twice.
    1. Parametric estimate
    2. Bottom-up estimate
    3. Analogous cost estimate
    4. You will probably notice some differences in the estimated values. Are these differences significant? What might cause the differences? If you were estimating a significant project in the future, which method(s) would you use and why?
    5. Your mother points out you should probably have valet parking, which will cost $500. Which estimate(s) will change?
Wedding Cost Estimates
Item Dollars
Groom's brother's wedding, last year, 175 guests, similar venue and style $20,300
Catering $65 per person
Photographer $1,500
Rental of hall $500
Clothing, bride $2,000
Clothing, groom

$750

Flowers $800
Other dcor items $500
Cake $500
Gifts for bridal party $80 each
Wedding planner $2,000
Wedding planner's estimate of typical cost for this kind of wedding $10,000 plus $75 per guest

2. Earned-value analysis. A project budget calls for the following expenditures:

Task Date Budgeted Amount
Build forms April 1 $10,000
April 1 $50,000
Pour foundation May 1 $100,000
May 1 $30,000
Frame walls June 1 $30,000

Remaining tasks

July 1 and beyond $500,000

Define each term in your own words, calculate these values for the above project, and show your work:

  1. Budgeted cost baseline (make a graph illustrating this one)
  2. Budget at completion (BAC)
  3. Planned value (PV) as of May 1
  4. Earned value (EV) as of May 1 if the foundation work is only two-thirds Everything else is on schedule.
  5. SV as of May
  6. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May
  7. Schedule performance index (SPI)
  8. Cost performance index (CPI)
  9. Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
  10. Estimate at completion (EAC)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality An Introduction

Authors: Robert A Brymer, Rhett BRYMER

16th Edition

1465299246, 9781465299246

More Books

Students also viewed these General Management questions