This assignment provides you with an opportunity to demonstrate the development and achievement of the following course learning outcomes: Construct a New Recreational Community Centre

This assignment provides you with an opportunity to demonstrate the development and achievement of the following course learning outcomes:
Construct a New Recreational Community Centre
The Town of Newfane has experienced rapid growth because of several new housing developments that have doubled the population over the last six years. In turn, this has led to a significant increase in year-over-year tax revenue for the Town. This has afforded the Town the opportunity to provide additional services to the community. However, the Town currently lacks the facilities to support such services. The regional council has recently voted to develop a Recreational Community Centre to be built on the municipal lands near the Town Hall.
Project Rationale
The new Centre will provide residents with facilities that will help bring the community together. It will also provide the opportunity to adequately support competitive supports with other towns and cities. The new complex will be state of the art and could be used to attract top tier athletes that the Town of Newfane was not previously able to recruit. The complex will continue to strengthen the Towns relationship with the local community through interaction programs such as hockey, swimming, and basketball camps as well as local fundraising events.
Project Objectives and Goals
The main objective of the project is to provide the local community with high quality sporting facilities to encourage both friendly and competitive events that will help promote the Towns team spirit. The goal of the project is to improve facilities so that they are at a standard and level to other prestigious facilities across the country.
Anticipated Benefits
Interest to utilize the facility by other athletes across the country
Increased revenue to the Town and the local community from events
Healthier and happier community
Creates a positive work-life balance for people
Improves the Towns reputation when they host national conferences
Project Alternatives
Most construction projects offer a number of alternatives to clients (e.g. bronze, silver, gold). A number of community consultation and collaborative sessions were held with the local community to develop a concrete list of facility amenities. The project team worked hard to finalize this list to avoid further changes during design and construction. After careful deliberation, the Town has decided to go with the gold alternative.
The gold package comes with a facility that will be modern, fit-for-purpose, and complete with sports and swimming facilities. It will be designed to meet the needs of todays public leisure users and the entire community.
The proposed 150,000 square foot facility will include the following:
Hockey rink
25m main swimming pool
Learner pool
Fitness suite
6 community multi-purpose studios
Gymnasium/ basketball court
1,400 parking spaces
Work Breakdown Structure (WBS)
Before developing a Gantt chart, its important to complete a Work Breakdown Structure (WBS) to illustrate the key components of the project. The complex will consist of a new 150,000 square foot facility with all of the elements mentioned above (e.g. hockey rink, 25m swimming pool, learner pool etc.) plus other components such as project management activities, lounges, and food concession areas. When breaking down your work, think about all these components as well as everything that goes into it (e.g. lighting, flooring, restrooms, seating, scoreboards, etc.)
Cost Estimates
Newfane Town Council initiated the project with funds secured from the new tax revenue generated because of the housing development and developer levies collected to support infrastructure projects. However, initial funding of $40M budgeted for the project were found to be insufficient to achieve the requirements and further funding was required. Town Recreation and Infrastructure Project Committees constructed a business plan that secured an additional $25M from Provincial grant for a total project budget of $65M.
Below is an estimated cost per square-foot (SF) to construct the Centre. Use it to determine what the cost is for each resource along with the % of total budget dedicated to each resource.
Item
Cost/SF per item
Total cost per Item
% of Total Budget per Item
Contractor Fees
$40
Architectural Fees
$12
Community Consultation Costs
$1
Cost of Materials
$300
Permit/Fees
$2
Cost of equipment Rentals
$50
Risks and Mitigation Strategies
Risks are inherent on every project. Building a large-scale Recreational Community Centre comes with own set of risks. When completing your report, you will need to think about different types of risks and how you will mitigate them.
Constraints
Below are some constraints for building the new Recreational Community Centre:
Project is slated to start on September of current year and expected to last 12 months
Work must be completed prior to the Grand Opening in September of the following year
Key decision makers may be difficult to contact during project (e.g. vacations, sick days)
Paired Assignment Peer Evaluation (10%)
The Paired Assignment has a Peer Evaluation. What that means is each person will evaluate his or her teammate in terms of their contribution. This is an INDIVIDUAL assignment so each of you MUST submit your own evaluation form. This will be in Moodle and the link to the file is located HERE.
Note: Failure to submit the form will result in a loss of 10% of your overall grade.
Paired Assignment PDF Report (20%)
Each report is expected to consist of the 7 following components.
Project Scope Statement (6 parts)
Project Objective Answers the questions of what, when and how much
Deliverables Tangible or intangible goods or services to be created
Milestones Major events to show segments of completed work
Technical Requirements Any performance specs needed for a product / service
Limits & Exclusions List Items outside of the scope to establish boundaries
Customer Reviews who is your point of contact? How will you manage expectations?
Work Breakdown Structure (WBS)
Create a WBS structure in a hierarchical format
Can be structured by phase or by deliverable (either one is fine)
Tasks should be:
Manageable authority and responsibility can be assigned
Measurable it should be easy to track progress on it
Independent not dependent on other activities
Rule of thumb:
Stay between 5 to 8 columns wide
Stay between 4 to 5 rows down
Gantt Chart
Create a Gantt chart for your Project
Note: the use of MS Project is not mandatory
Use the template provided or any software available to assist in building the Gantt (e.g. PowerPoint, Visio, Excel, PowerPoint or MS Word)
Use the WBS created above to match the breakdown of the Gantt Chart
Include key deliverables and milestones
Conduct research when necessary and use industry knowledge when appropriate
Budget
Use the information provided in the "cost table" above to create a budget for this project
Develop the budget in an excel spreadsheet or word document (either is fine)
Risks and Mitigation Strategies
Planning what risks come with planning a greenfield (undeveloped) project with nearby houses and substantial change?
Schedule Delays what will be the impact of a delay in the project? How can you minimize it? How can you avoid disruption to the local community? What will be your Plan B?
Cost Increases sometimes the prices of material increase due to an increase in demand (e.g. raw material such as wood, steel, glass). How can you avoid this problem?
Environmental since this is a greenfield project, what kind of an impact could this have to the environment and, potentially, to endangered species? How can you mitigate that? What about flood risk?
Conclusion
What were your Key Findings?
Will the project finish on time and within budget? Why or why not?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

College Accounting Chapters 1-29

Authors: John J. Wild, Vernon J. Richardson, Ken W. Shaw

2nd Edition

0077398173, 978-0077398170

More Books

Students explore these related Accounting questions