This excerpt from an Integrated Master Schedule (IMS) has been designed to show what sort of information that can help identify schedule drivers? (IMAGE DESCRIPTION:
This excerpt from an Integrated Master Schedule (IMS) has been designed to show what sort of information that can help identify schedule drivers? (IMAGE DESCRIPTION: A Gantt chart for a sample project displays a project with 8 tasks, plus project start and project end milestones. All tasks have a finish-to-start relationship with their successors, unless otherwise noted. The project starts on January 1 2015 and finishes on January 29 2015. Task A starts on January 1 2015, finishes on January 5 2015, has 5 days of float, and has Task D as a successor. Task B starts on January 4 2015, finishes on January 7 2015, has zero float, and has Task E as a successor. Task C starts on January 4 2015and finishes on January 7 2015, has zero float, and has Task F as a successor. Task D starts on January 6 2015, finishes on January 15 2015, has zero float and has Task G as a successor. Task E starts on January 8 2015, finishes on January 20 2015, has zero float, and has Task H as a successor. Task F starts on January 8 2015, finishes on January 21 2015, has zero float, and has Task H as a successor with a finish-to-finish relationship. Task G starts on January 16 2015, finishes on January 25 2015, has 7 days of float and has Task H as a successor. Task H starts on January 29 2015, finishes on January 29 2015, has zero float and has a finish-to finish relationship with its successor, the project end. Tasks B, E, H, and the project end milestone are all color-coded red.) |
The IMS does not provide information on schedule drivers but merely provides updates to the schedule dates. |
This chart shows the baseline schedule, and all tasks on the baseline schedule are drivers because all tasks have 0 float. |
This chart provides information about the schedule critical path, and tasks on the critical path are schedule drivers |
This chart provides information about the schedule critical path, but it is not clear from this what tasks are schedule drivers. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started