This exercise will help you apply EVM concepts to a real - world project scenario and assess its performance. It will also give you practice

This exercise will help you apply EVM concepts to a real-world project scenario and assess its performance. It will also give you practice in calculating and interpreting key EVM metrics.
Scenario: You are a project manager overseeing the construction of a new office building. The project is well underway, and you want to assess its performance using Earned Value Management (EVM) techniques. Below are the project details and data you have collected.
Project Details:
- Project Name: ABC Office Building Construction
- Total Budget (BAC - Budget at Completion): $200,000
- Planned Duration: 12 months
- Status Date: End of Month 6(You are halfway through the project)
- Number of Work Packages: 10
Data at the Status Date (End of Month 6):
- Planned Value (PV): $100,000
- Earned Value (EV): $80,000
- Actual Cost (AC): $110,000
Objective: Provide a written analysis of the project's performance based on the calculated metrics.
Tasks:
1). Calculate the following Earned Value Management (EVM) metrics for the XYZ Office Building Construction project at the end of Month 6:
- Cost Variance (CV)
- Schedule Variance (SV)
- Cost Performance Index (CPI)
- Schedule Performance Index (SPI)
- Estimate at Completion (EAC) assuming the current performance will continue
- New completion date
- Estimate to Completion (ETC)
- Variance at Completion (VAC)= BAC - EAC
2). Interpret the calculated metrics and provide insights into the project's performance at the halfway point. Is the project on budget, ahead of schedule, or behind schedule? What corrective actions might be necessary?
You DON'T need to comment on other post. Do not modify your post after posting.
You must start a thread before you can read and reply to other threads

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management Formulation Implementation And Control

Authors: John A Pearce , Richard B Robinson Jr

9th Edition

0072980079, 978-0072980073

More Books

Students also viewed these General Management questions