This graph depicts a time-phased performance measurement baseline (PMB) with cumulative budgeted cost for work scheduled (BCWS), budgeted cost for work performed (BCWP), and actual
This graph depicts a time-phased performance measurement baseline (PMB) with cumulative budgeted cost for work scheduled (BCWS), budgeted cost for work performed (BCWP), and actual cost of work performed (ACWP). Given this information, which of the following is true at Time Now?
(IMAGE DESCRIPTION: PMB graph with BCWS plotted from contract start through contract end. BCWP and ACWP are plotted from contract start through time now. At time now BCWS is $4,000, BCWP value is $2,000, and ACWP value is $6,000.)
DAU 3) This graph depicts a time-phased performance measurement baseline (PMB) with cumulative budgeted cost for work scheduled (BCWS), budgeted cost for work performed (BCWP), and actual cost of work performed (ACWP). Given this information, which of the following is true at Time Now? (IMAGE DESCRIPTION: PMB graph with BCWS plotted from contract start through contract end. BCWP and ACWP are plotted from contract start through time now. At time now BCWS is $4,000, BCWP value is $2,000, and ACWP value is $6,000.) Schedule variance (SV) is unfavorable, and cost variance (CV) is favorable Schedule variance (SV) and cost variance (CV) are both favorable Cost variance (CV) and schedule variance (SV) are both unfavorable Schedule variance (SV) is favorable and cost variance (CV) is unfavorable https://learn.dau.mil/Atlas2/html/testengine/TestGeneration/test_main1.jsp[8/11/2017 7:10:58 AM]Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started