Question

1 Approved Answer

This is a multiselect question, at least one answer is correct, but select ALL of the correct answers A . A major factor for developing

This is a multiselect question, at least one answer is correct, but select ALL of the correct answers
A. A major factor for developing greater accuracy for project cost estimates is to cost the project on key major deliverables vs WP's
B. Using $500 US dollars per cubic meter would be an example of a parametric estimate
C. A homeowner changing the quality of items in their new house after the started, like the quality of the granite and wood would be an example of specification change problems with cost estimations estimations

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic management concepts

Authors: Fred david

13th Edition

9780136120988, 136120997, 136120989, 978-0136120995

More Books

Students also viewed these General Management questions

Question

What are the two primary ways in which health care is rationed?

Answered: 1 week ago