Question

1 Approved Answer

This is a two-part question. Please answer both for my assessment thanks: Problem 6a An assembly line with 17 tasks is to be balanced. The

This is a two-part question. Please answer both for my assessment thanks:

Problem 6a An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day. a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.) Minimum cycle time minutes Maximum cycle time minutes b. What range of daily output is theoretically possible for the line? (Round your answers to 1 decimal place. Enter the smaller value in the first box and the larger value in the second box.) Range of output to units/day c. What is the minimum number of workstations needed if the maximum output rate is to be sought? (Round up your answer to the next whole number.) Minimum number of workstations d. What cycle time will provide an output rate of 125 units per day? (Round your answer to 1 decimal place.) Cycle time min/cycle e. What output potential will result if the cycle time is (1) 9 minutes? (2) 15 minutes? Cycle Time Potential Output (1) units (2) units

Then

Problem 6b A manager wants to assign tasks to workstations as efficiently as possible, and achieve an hourly output of 4 units. The department uses a working time of 56 minutes per hour. Assign the tasks shown in the accompanying precedence diagram (times are in minutes) to workstations using the following rules: a. In order of most following tasks. Tiebreaker: greatest positional weight. Work Station Tasks I (Click to select) D, B, C A, G F, A, G E, H I II (Click to select) F, A, G D, B, C D E, H I III (Click to select) E, H D, B, C H I F, A, G IV (Click to select) H I B,E E, H F, A, G b. In order of greatest positional weight. Work Station Tasks I (Click to select) F, G C, D F, D D, C G, H II (Click to select) G, A, B E, H F, A, G B, C G, H III (Click to select) A B,E C, E D, C, F F, G IV (Click to select) H, I B,E A H G c. What is the efficiency? (Round your answer to 2 decimal places. Omit the "%" sign in your response.) Efficiency %

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_step_2

Step: 3

blur-text-image_step3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions

Question

1. What are your creative strengths?

Answered: 1 week ago

Question

What metaphors might describe how we work together?

Answered: 1 week ago